TUPOJO18 Cavity Qualification and Production Update for SNS-PPU Cryomodules at Jefferson Lab 387
 
  • P. Dhakal, E. Daly, J.F. Fischer, N.A. Huque
    JLab, Newport News, Virginia, USA
  • M.P. Howell
    ORNL, Oak Ridge, Tennessee, USA
  • J.D. Mammosser
    ORNL RAD, Oak Ridge, Tennessee, USA
 
  Funding: This manuscript has been authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
The Proton Power Upgrade (PPU) project at Oak Ridge National Lab’s Spallation Neutron Source (SNS) currently being constructed will double the proton beam power capability from 1.4 to 2.8 MW by adding seven cryomodules, each containing four six-cell high-beta (β = 0.81) superconducting radio frequency cavities. Research Instruments, located in Germany, built and processed the cavities at the vendor site, including electropolishing as the final active chemistry step. Twenty-eight cavities for seven cryomodules and an additional four cavities for a spare cryomodules were delivered to Jefferson Lab and first qualification tests were completed on all cavities as received from the vendor. The performance largely exceeded the requirements on quality factor and accelerating gradient. Here we present the status of initial cavity qualification tests, rework on unqualified cavities and final cavity qualification with helium vessel prior to installation in cryomodules. In addition, an update on cryomodule production is presented.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2022-TUPOJO18  
About • Received ※ 23 August 2022 — Revised ※ 29 August 2022 — Accepted ※ 01 September 2022 — Issue date ※ 09 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOJO19 Progress on the Proton Power Upgrade Project at the Spallation Neutron Source 390
 
  • M.S. Champion, C.N. Barbier, M.S. Connell, J. Galambos, M.P. Howell, S.-H. Kim, J.S. Moss, B.W. Riemer, K.S. White
    ORNL, Oak Ridge, Tennessee, USA
  • E. Daly
    JLab, Newport News, Virginia, USA
  • N.J. Evans, G.D. Johns
    ORNL RAD, Oak Ridge, Tennessee, USA
  • D.J. Harding
    Fermilab, Batavia, Illinois, USA
 
  Funding: This material is based upon work supported by the U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under contract number DE-AC05-00OR22725.
The Proton Power Upgrade Project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion of the project, 2 MW of beam power will be available for neutron production at the existing first target station with the remaining beam power available for the future second target station. The project will install seven superconducting RF cryomodules and supporting RF power systems and ancillaries to increase the beam energy to 1.3 GeV . The injection and extraction region of the accumulator ring will be upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. Equipment is being received from vendors and partner laboratories, and installation is underway with three major installation outages planned in 2022-2024. The project is planned to be completed in 2025.
 
poster icon Poster TUPOJO19 [1.361 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2022-TUPOJO19  
About • Received ※ 22 August 2022 — Revised ※ 15 August 2022 — Accepted ※ 31 August 2022 — Issue date ※ 01 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)