Paper |
Title |
Page |
MOPOPA15 |
Three Years of Operation of the SPIRAL2 SC LINAC- RF Feedback |
98 |
|
- M. Di Giacomo, M. Aburas, P.-E. Bernaudin, O. Delahaye, A. Dubosq, A. Ghribi, J.-M. Lagniel, J.F. Leyge, G. Normand, A.K. Orduz, F. Pillon, L. Valentin
GANIL, Caen, France
- F. Bouly
LPSC, Grenoble Cedex, France
- S. Sube
CEA-DRF-IRFU, France
|
|
|
The superconducting LINAC of SPIRAL2 at the GANIL facility has been in operation since October 2019. The accelerator uses 12 low beta and 14 high beta supercon-ducting quarter wave cavities, cooled at 4°K, working at 88 MHz. The cavities are operated at a nominal gradient of 6.5 MV/m and are independently powered by a LLRF and a solid-state amplifier, protected by a circulator. Pro-ton and deuteron beam currents can reach 5 mA and beam loading perturbation is particularly strong on the first cavities, as they are operated at field levels much lower than the nominal one. This paper presents a feedback after three years of oper-ation, focuses on the RF issues, describing problems and required improvement on the low level, control and pow-er systems
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-LINAC2022-MOPOPA15
|
|
About • |
Received ※ 14 August 2022 — Revised ※ 17 August 2022 — Accepted ※ 01 September 2022 — Issue date ※ 02 September 2022 |
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
TU2AA02 |
SPIRAL2 Final Commissioning Results |
314 |
|
- A.K. Orduz, P.-E. Bernaudin, M. Di Giacomo, R. Ferdinand, B. Jacquot, O. Kamalou, J.-M. Lagniel, G. Normand, A. Savalle
GANIL, Caen, France
- D.U. Uriot
CEA-DRF-IRFU, France
|
|
|
The commissioning of SPIRAL2 was carried out in different steps and slots from 2014 to end 2021. In a first phase, the proton-deuteron and heavy ion sources, LEBT lines and RFQ were commissioned and validated with A/Q=1 up to 3 particles. The validation of the MEBT (between the RFQ and the linac, including the Single Bunch Selector), linac and HEBT lines (up to the beam dump and to the NFS experimental room) started on July 2019, when GANIL received the authorization to operate SPIRAL2. The linac tuning is now validated with H+, 4He2+ and D+ and nominal H+ and D+ beams were sent to NFS for physics experiments. The main results obtained during the commissioning stages and the strategy used by the commissioning team are presented.
|
|
|
|
|
|
please see instructions how to view/control embeded videos |
|
|
Slides TU2AA02 [3.724 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-LINAC2022-TU2AA02
|
|
About • |
Received ※ 24 August 2022 — Revised ※ 29 August 2022 — Accepted ※ 01 September 2022 — Issue date ※ 02 September 2022 |
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|