Author: Masa, S.
Paper Title Page
TUPOJO12 Development of Emittance Meter Instrument for MYRRHA 368
 
  • A. Rodríguez Páramo, I. Bustinduy, S. Masa, R. Miracoli, V. Toyos, S. Varnasseri
    ESS Bilbao, LEIOA, Spain
  • L. De Keukeleere, F. Doucet, A. Ponton, A. Tanquintic
    SCK•CEN, Mol, Belgium
  • J. Herranz
    Proactive Research and Development, Sabadell, Spain
 
  For the commissioning of the Myrrha proton Linac an Emittance Meter Instrument (EMI) has been foreseen. The EMI will be installed in a dedicated test bench for linac commissioning. The test bench will be initially placed after the RFQ with energies of 1.5 MeV, and in later stages moved to other sections of the Normal Con-ducting Linac for operation at 6 and 17 MeV. The Myrrha EMI will be composed by two slit and grid subsystems for measurement of the phase space in the horizontal and vertical directions. For collimating the beam, graphite slits are used, and the beam aperture is measured in the SEM grids placed downstream. Then, the control system performs signal amplification, data acquisition, and motion control, with the different sys-tems integrated in an EPICs IOC. The system, manufactured by ESS-Bilbao and Proac-tive R&D, has been tested on the ESS-Bilbao 45 keV and soon will be integrated in Myrrha facilities. We present the EMI design, with irradiation analysis and emittance reconstruction, and the integration tests results.  
poster icon Poster TUPOJO12 [1.141 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2022-TUPOJO12  
About • Received ※ 19 August 2022 — Revised ※ 30 August 2022 — Accepted ※ 02 September 2022 — Issue date ※ 07 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOPA03 Status and RF Devopments of ESS Bilbao RFQ 410
 
  • N. Garmendia, I. Bustinduy, A. Conde, P.J. González, A. Kaftoosian, J. Martin, S. Masa, J.L. Muñoz, Á. Rodríguez Páramo
    ESS Bilbao, Zamudio, Spain
 
  Within the framework of the plans for study of a light-ion linear accelerator, ESS Bilbao is manufacturing a radio frequency quadrupole (RFQ) aimed at accelerating up to 3 MeV the protons generated in the ion source. The progress made and the difficulties encountered with the RFQ are discussed in this paper. A power coupler proto-type for the RFQ has been developed while several me-chanical constraints were also studied in the final cou-pler. This prototype operates at a lower power, then it can work using PEEK window for the vacuum interface and it does not require neither brazing nor cooling system. Also, a complete RF test stand is being implemented to perform the high-power conditioning in traveling and standing wave mode, to verify the power handling capa-bility of the coupler and its thermal behaviour. The RF test stand, based on EPICS environment, can provide up to 2 MW peak power at 352.2 MHz in a pulse operation of 14 Hz and a duty cycle of 4.9%.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2022-TUPOPA03  
About • Received ※ 09 August 2022 — Revised ※ 28 August 2022 — Accepted ※ 30 August 2022 — Issue date ※ 02 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)