Author: Phillips, G.
Paper Title Page
TU2AA04 Commissioning of IFMIF Prototype Accelerator Towards CW Operation 319
 
  • K. Masuda, T. Akagi, A. De Franco, T. Ebisawa, K. Hasegawa, K. Hirosawa, J. Hyun, T. Itagaki, A. Kasugai, K. Kondo, K. Kumagai, S. Kwon, A. Mizuno, Y. Shimosaki, M. Sugimoto
    QST Rokkasho, Aomori, Japan
  • T. Akagi, Y. Carin, F. Cismondi, A. De Franco, D. Gex, K. Hirosawa, K. Kumagai, S. Kwon, K. Masuda, I. Moya, F. Scantamburlo, M. Sugimoto
    IFMIF/EVEDA PT, Aomori, Japan
  • L. Antoniazzi, L. Bellan, M. Comunian, A. Facco, E. Fagotti, F. Grespan, A. Palmieri, A. Pisent
    INFN/LNL, Legnaro (PD), Italy
  • F. Arranz, B. Brañas, J. Castellanos, D. Gavela, D. Jimenez-Rey, Á. Marchena, J. Mollá, P. Méndez, O. Nomen, C. Oliver, I. Podadera, D. Regidor, A. Ros, V. Villamayor, M. Weber, C. de la Morena
    CIEMAT, Madrid, Spain
  • N. Bazin, B. Bolzon, N. Chauvin, S. Chel, J. Marroncle
    CEA-IRFU, Gif-sur-Yvette, France
  • P. Cara, Y. Carin, F. Cismondi, G. Duglue, H. Dzitko, D. Gex, A. Jokinen, I. Moya, G. Phillips, F. Scantamburlo
    F4E, F4E, Germany
  • A. Mizuno
    JASRI/SPring-8, Hyogo-ken, Japan
  • Y. Shimosaki
    KEK, Ibaraki, Japan
 
  Construction and validation of the Linear IFMIF Prototype Accelerator (LIPAc) have been conducted under the framework of the IFMIF/EVEDA project. The LIPAc consists, in its final configuration, of a 100 keV injector and the world longest 5 MeV RFQ accelerator, followed by a MEBT with high space charged and beam loaded re-buncher cavities, an HWR-SRF linac, HEBT with a Diagnostic Plate, ending in a Beam Dump (BD) designed to stop the world highest deuteron current of 125 mA CW at 9 MeV. The beam commissioning at a low duty cycle of ~0.1 % led to a successful RFQ acceleration of 125 mA and 5 MeV beam in 2019. The following beam commissioning phase was initiated in July 2021 with a temporary transport line replacing the SRF linac. The major goals of this phase are to validate the RFQ, MEBT and BD performances up to CW and to characterize the beam properties in preparation to the final configuration with the SRF linac. This paper will present progresses made in this phase so far, such as a low-current and low-duty beam commissioning completed in Dec. 2021, CW operation campaign of the injector towards the nominal beam current, and RF conditioning of the RFQ towards CW.  
video icon
 
  please see instructions how to view/control embeded videos  
slides icon Slides TU2AA04 [6.731 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2022-TU2AA04  
About • Received ※ 27 August 2022 — Revised ※ 31 August 2022 — Accepted ※ 02 September 2022 — Issue date ※ 08 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)